The contractors have installed sewer and water utilities in the Lucy Ridge Lane and Topaz Circle area, and have completed the street construction, with exception of curb and gutter, which couldn’t get installed due to late season weather conditions.  As such, a temporary bituminous surface is being installed in order to maintain construction access over the winter.  Permits for home construction are expected to begin over the next few weeks.

November 18, 2020

Contractors plan to begin hauling sand and gravel to build the streets within the development starting on Thursday.  There will be a significant amount of trucks hauling over the next few days.  The developer has been instructed to watch their speeds and drive cautiously.   There may be trucks waiting temporarily in the neighborhood, but they have been instructed to minimize any temporary staging and utilize re-routing and staging outside of the neighborhood.  There has also been planning to have a street sweeper on-site at the end of each day.  The developer has indicated there may be a need to haul on Saturday, but they are trying to avoid that scenario. This information has also been distributed to the head of the Lucy Ridge HOA.

November 9, 2020-Change

The contractor has cancelled the water shut down for today due to pending rain.  Residents are being re-notified for tomorrow.

November 9, 2020

On Monday, November 9th, construction crews will be turning off the water between 9:00 AM to 1:00 PM to make connections to the water main.  The homes that will be affected are listed below.  Please plan accordingly.  

Properties:

6895 LUCY RIDGE LN
6915 LUCY RIDGE LN
6935 LUCY RIDGE LN
6900 LUCY RIDGE LN

The contractors will try to keep the disruption to a minimum during this time.  We are sorry for this inconvenience.