- Home
- Your Government
- Departments
- Engineering / GIS
- Projects
- Street Projects
- 2021 City Pavement Rehabilitation Project
2021 City Pavement Rehabilitation Project
-
Matt Petite
Engineering Technician/ Construction ManagerPhone: (952) 227-1166 Cell: (612) 358-7085
-
George Bender
Assistant City EngineerPhone: (952) 227-1164
Overview
The adoption of a new franchise fee has allowed the City to invest substantially more in the maintenance and preservation of our local roads, which can be seen from the scope of the 2021 City Pavement Rehabilitation project. This project will incorporate multiple roadway treatments (mill & overlay, full depth reclamation, etc.) depending on the condition of the road for each area, along with minor spot repairs on existing utilities.
A total of seven (7) miles of roadway is proposed to be improved, so the project has been broken up into six areas; the Lake Lucy Road area (east of Powers Boulevard), Choctaw Circle area, Kurvers Point Road area, Marsh Drive area, Redwing Lane area, and the Trappers Pass area. The project is anticipated to begin in the summer of 2021, with work scheduled to be completed in the fall of 2021. Residents that utilize the streets within the project areas will be notified if access is limited.
This project was originally planned for 2020, however In light of recent state funding losses stemming from the COVID-19 pandemic and out of concern for the potential negative economic impact assessments might have on some Chanhassen residents, the City Council voted to postpone the planned road construction project and reassess at a later time. It is now scheduled to take place during the 2021 construction season.
Click Here for a full map of the project areas.
Related Resources
Assessment Practice
The City of Chanhassen's Assessment Practice is intended to provide direction to City Staff in preparation of assessment rolls for public improvements, to ensure fair and consistent treatment of all properties within the City of Chanhassen.
Pavement Management
Pavement Management Questions/Answers
Project Updates
January 21, 2022
TRAPPERS PASS AREA: The removal of sediment from the pond at Trappers Pass and Oxbow bend has been completed and the storm sewer improvements are finishing up today. Temporary stabilization to the affected areas is scheduled to take place next week and final restoration is expected to be completed by June 3, 2022.
Project Areas
This project is divided into six neighborhood areas. Trappers Pass is the largest area and will be divided into two construction phases.
Here are the Estimated Construction Dates for Each Area:
Lake Lucy Road area | May 17 - July 15 |
Redwing Lane area | June 11 - July 24 |
Choctaw Circle area | June 22 - Aug 5 |
Trappers Pass-1 area (See Map) | June 30 - Oct 7 |
Trappers Pass-2 area (See Map) | July 26 - Oct 7 |
Marsh Drive area | Aug 23 - Nov 5 |
Kurvers Point Road area | Sept 20 - Nov 4 |
Substantial completion is expected by November 2021. Stormwater pond clean-out work will occur in the Trapper's Pass area during the winter of 2021/2022. Final restoration is planned during the spring of 2022.
Project Schedule
Revised for 2021 Project Start | |
---|---|
Accept Feasibility Report/Call Public Hearing | January 11, 2021 |
Public Hearing | January 25, 2021 |
Approve Plans & Specifications/Authorize Bidding | February 8, 2021 |
Bid Opening | March 12, 2021 |
Public Information Open House | April 14, 2021 |
Assessment Hearing/Award Contract | April 26, 2021 |
Start Construction | May 2021 |
Substantial Completion | November 2021 |
Project Notification Disclaimer |
---|
Due to the variability of construction, updates typically do not include specific details such as day-to-day scheduled activity. The City's inspector or contractor will notify occupants directly if they will be impacted by a utility service shut down (example: water shutoff), or work (such as excavation or new curb) that will impede access to the property for a period of hours or days. |